The
scope of substation work in Atlantic Canada completed by EUS since 2007
includes greenfield construction on wind farms and other sites, and
maintenance and upgrades to existing substations. EUS offers
Engineering, Procurement and Construction (EPC) services for
construction of new substations, build-to-print construction services
and supply of skilled resources and equipment necessary to complete
them.
Our capabilities in transmission line construction and maintenance include:
- Project Management
- Engineering
- Material procurement and Management
- Civil Construction
- Grounding
- Steel Erection
- Control building, cabling and terminations
- Electrical equipment installation
- Electrical bus work
- Testing and commissioning
Substation and Control Building Construction Project History
Glen Dhu Wind Farm
Dates: Access to site (September 2009). Substantial completion (November 2009)
EUS
completed EPC for the interconnection substation between Glen Dhu Wind
Energy 34.5 kV wind farm collector system and a 138kV Nova Scotia Power
transmission line. Construction activities included Civil, Grounding,
Control Cabling, Control Building, 34.5kV Electrical Equipment, 138kV
electrical equipment and the main power transformer. EUS was also
responsible for development and execution of the substation testing and
commissioning program.
Digby Wind Farm
Dates: Access to site (August 2010). Substantial completion (December 2010)
EUS
completed EPC for the interconnection substation between Nova Scotia
Power’s 34.5 kV wind farm collector system and a 69kV Nova Scotia Power
transmission line. Construction activities included Civil, Grounding,
Control Cabling, Control Building, 34.5kV Electrical Equipment, 69kV
Electrical Equipment and the Main Power Transformer. EUS was also
responsible for development and execution of the substation testing and
commissioning program.
Dalhousie Mountain Wind Farm
Dates: Access to site (July 2009). Substantial completion (December 2009).
EUS
completed EPC for the interconnection substation between RMS Energy
34.5 kV wind farm collector system and a 230kV Nova Scotia Power
transmission line. Construction activities included Civil, Grounding,
Control Cabling, Control Building, 34.5kV Electrical Equipment and 230kV
Electrical Equipment. EUS was also responsible for development and
execution of the substation testing and commissioning program.
Caribou Mountain Wind Farm
Dates: Access to site (April 2009). Substantial completion (August 2009).
EUS
completed EPC for the interconnection substation between GDF Suez 34.5
kV wind farm collector system and a 138kV New Brunswick Power
transmission line. Construction activities included Civil, Grounding,
Control Cabling, Control Building, 34.5kV Electrical Equipment and 138kV
Electrical Equipment. EUS was also responsible for development and
execution of the substation testing and commissioning program.
Lingan Wind Farm
Dates: Access to site (April 2006). Substantial completion (June 2006).
EUS
completed Construction for the interconnection substation between Cape
Breton Power Ltd. 25kV wind farm collector system and a 69kV Nova
Scotia Power transmission line. Construction activities included Civil,
Grounding, Control Cabling, Control Building, 25kV Electrical
Equipment and 69kV Electrical Equipment.
Nova Scotia Power Inc.
Dates: Contract start date 1992, and remains ongoing.
EUS
has completed new construction, maintenance, upgrades and expansions
for substations throughout Nova Scotia and of all different sizes and
voltages.
New Brunswick Power
Dates: Contract start date 2001, and remains ongoing.
EUS
has completed new construction, maintenance, upgrades and expansions
for substations throughout New Brunswick and of all different sizes and
voltages.