Project name: West Cape Transmission Line Build
Location: Prince Edward Island
Customer name: Maritime Electric
Type of project: Transmission Line Construction and Maintenance

EUS was awarded the contract from Maritime Electric to construct a 70km 138kV transmission line on wood structures from GDF Suez’s 100MW West Cape Wind Farm to the substation in Summerside, PEI. The project began in October 2008 and was energized in February 2009.