Project Details

Project name: Hendrix Distribution Line
Location: Summerside, Prince Edward Island
Customer name: City of Summerside
Type of project: Distribution Line Construction and Maintenance

EUS was awarded the design/construct contract from the City of Summerside for a 7km 34.5kV Hendrix line from a 12MW wind farm in PEI to the Summerside substation. The project began in June 2009 and was energized in November 2009.